-Updated 28 December 2012.
Construction works on Maputo Airport's new Domestic Terminal have been concluded with functionality testing to be run from August onwards. The final touches now being applied include the cooling system, electrical appliances, safety equipment, escalators and an FIDS (flight information display system).
The terminal is then expected to be officially inaugurated and handed over in October according to Project coordinator Acácio Tuendue.
"Since 2010 both domestic and international flights have been taking
off from the international terminal, with the Chinese company AFECC
commencing construction in April last year.
Speaking to reporters on Tuesday, project manager Acacio Tuende said
that the domestic terminal will be tested in July, with operations
scheduled to start in August. The terminal is due to be inaugurated in
October.
This is part of a major project for the expansion and upgrading of
the airport, budgeted at 132 million US dollars. Of this amount, 32
million dollars will be spent on the domestic terminal."
Read More Here [AllAfrica]
The First Phase of renovating Maputo International Airport came to a conclusion with the inauguration of the new International Terminal in November 2010. Phase Two commenced shortly after when the old domestic terminal (that is, the old International Terminal built in the 60s) was torn down to make way for the new one costing USD$36million, built by Chinese firm Anhui Foreign Economic Construction (Group) Co. Ltd. (AFECC) as part of The Airports Company of Mozambique's renovation and rejuvenation program. A new Control Tower is also expected to be completed.
Phase Three of the project is to follow with the renovation of the main runway, aprons and taxiways.
▪ OVERVIEW ▪
Situated 3km northwest of Maputo, the Mozambican capital, Maputo International Airport is the largest airport in Mozambique serving roughly 500'000 passengers per year. However, since independence in 1975 from colonial power Portugal and the bitter civil war that followed, little has been done to maintain, let alone, upgrade existing aeronautical infrastructure - until now.
Phase I
Phase One expansion and modernisation of Maputo International Airport began in 2007 with the construction of new
VIP/Presidential, Cargo and International Passenger Terminals aimed at boosting passenger capacity from 300'000 passengers per year, to 900'000 a year. it was built at a
cost of USD$75million with funding coming in the form of a low interest Chinese loan. The main contractor was
Anhui Foreign Economic Construction (Group) Co. Ltd. (AFECC), China.
Phase One was completed in November 2010.
Phase II
Phase Two consisted of first demolishing the old International Terminal which had since been turned into the Domestic Terminal, and then, the construction of a New Domestic Terminal and a new Control Tower budgeted to cost USD$36million. Construction of all buildings is complete, with the Control Tower Equipment tender having been awarded and subsequently, about to be fulfilled.
Phase Two is now undergoing testing and evaluation intended to anticipate, identify and correct any possible problems at the terminal that may occur when the terminal is used by operators and passengers.
Until the completion of works, both domestic and international flights from Maputo will operate out of the new International Terminal.
▪ PHASE II AIRPORT FACILITIES & SPECIFICATIONS ▪
-
Main contractor: Anhui Foreign Economic Construction (Group) Co. Ltd. (AFECC)
- Architects: L-Wong Consulting, Maputo, Mozambique
- Objective: New Domestic Terminal Building, New Control Tower Building & Equipment.
- Area: 13,200 square metres
- Intended Capacity: 2 million passengers/annum (580 passengers at peak hours, with 300 in the departure lounge and 280 in arrivals.)
- Facilities: 14 check-in counters, offices, a main hall and commercial area, a health clinic, restaurants, pharmacies, and other facilities.
Phase III
Phase Three will commence when Phase Two is successfully completed and will entail the renovation of Maputo's existing 3'660m (12'007ft) solitary runway, apron and taxiways.
▪ ARCHITECTURAL RENDERINGS ▪
|
Maputo Airport (Domestic L, International R) |
|
Zoom in of Terminals. |
|
Overall Airport Rendering (L-wong) |
|
VIP/Presidential Terminal (Phase I) |
|
Overall Project Rendering (AdM) |
▪ PROGRESS THUS FAR ▪
|
Maputo Airport International Terminal |
|
Inside Maputo Airport International Terminal (Bie) |
|
Maputo Airport International Terminal (Alama) |
▪ The Completed A & B Terminals (Updated August 2012) ▪
|
Both Terminals Complete (alama) |
|
Completed International (B) Terminal (alama) |
|
|
|
Completed Domestic (A) Terminal (alama) |